IMPERIAL OIL (IOL) PROJECT
MORGAN CONSTRUCTION & ENVIRONMENTAL INC.PILE CUTTING PROPOSAL
A field-ready plan using Innovative Well Abandonment’s high-pressure water jet cutting system with dual pumping systems.
Compliant








01 — Project Area
IMPERIAL OIL COLD LAKE
Morgan Construction and Environmental Ltd. — Imperial Oil project northwest of Cold Lake, Alberta
NORTHWEST OF COLD LAKE
Project area northwest of Cold Lake. The scope covers approximately 4 km of above-ground pipeline supported by 6-inch, 8-inch and 10-inch piles spaced approximately 10 m apart. Morgan shears the pipes and I-beams, trimming I-beams to approximately 1 ft above ground; Innovative Well Abandonment cuts piles to approximately 1 ft above surface, then water jet cuts them 2 m below surface. Backfilling uses client-supplied material.
Applications
01
Pipelines
02
Gas plants and oil sands sites
03
Production facilities
04
Tank farms
05
Well sites
02 — Technology
Cutting Technology & Execution
High-pressure water jet cutting, and the sequence the crews follow on each pile.
High-Pressure Water Jet Cutting
A high-pressure water jet cutting system with dual pumping systems cuts through pile walls without heat or sparks.
Minimal Ground Disturbance
Cuts are made from inside the pile, with minimal to no disturbance to the surrounding ground.
2 m Specified Depth
Piles on this project will be cut 2 metres below surface. The system can reach 10 metres or more.
External Cutting Tools
External cutting tools are available as an additional capability where internal access is limited.
Execution Sequence
- 01
Morgan shears the pipes and I-beams, trimming I-beams to approximately 1 foot above ground.
- 02
IWA cuts piles to approximately 1 foot above surface, then water jet cuts them 2 metres below surface.
- 03
Internal debris is checked and cleared, with steaming if required.
- 04
IWA completes a 360-degree water jet cut 2 metres below surface.
- 05
Morgan pulls the piles with a tracked excavator.
- 06
IWA backfills the holes with a backhoe using client-supplied material.
03 — Rates
Pricing & Rate Options
Two mutually exclusive pricing options. The client selects one option in advance of mobilization.
Option A — Per Pile
Per Pile Cut
$0$200
per 6-inch pile cut
Est. 8 piles/hour
$0$275
per 8-inch pile cut
Est. 6 piles/hour
$0$300
per 10-inch pile cut
Est. 5 piles/hour
Option B — Day Rate
Productive Field Day
$0$12,000
Per 10-hour productive field day. Unlimited cutting during those hours; travel and subsistence extra.
Choose one option in advance — options are mutually exclusive
Supporting Rates
Cut truck and crew mobilization / demobilization
$0.00$375.00per hour
Cut truck and crew daily travel
$0.00$375.00per hour
Support truck mobilization and in-field travel
$0.00$2.00per km
Subsistence
$0 if camp is provided.
$0.00$275.00per person / day
Standby outside IWA’s control
$0.00$450.00per hour
Case 590 backhoe with operator
$0.00$160.00per hour
General labour
$0.00$70.00per hour
Optional charge - centralizer and cap
$0.00$85.00each
04 — Assumptions
Assumptions & Conditions
The basis of estimate for this proposal, including access, schedule and operating conditions.
Backfill Material
Backfilling uses client-supplied material (sand or other suitable fill). IWA will backfill every hole using a Case 590 backhoe.
Pile Removal
Morgan will provide the tracked excavator and pull each pile once IWA completes the cut.
Pipeline Removal
Morgan will shear the pipes and I-beams, trimming I-beams to approximately 1 foot above ground. IWA then performs all pile cutting.
Pile Interiors
Steaming may be required to clear debris from pile interiors before the internal cut can be completed.
Cut Depth
Piles will be cut 2 metres below surface with a 360-degree high-pressure water jet cut.
Pricing Option
The client will select either per-pile pricing (Option A) or the day rate (Option B) before mobilization.
Accommodation
Subsistence is charged at $275 per person per day, or $0 where camp accommodation is provided.
Site Access and Safety
The client will provide site access along the right-of-way, site orientation, and any required gas-detection and communication devices.
05 — Contacts
Contacts & Next Steps
Leads on both sides of the project, and what has to close before the crew mobilizes.

Morgan Construction and Environmental Ltd.
Address
Calgary Project OfficeSuite 200, 809 Manning Road N.E,Calgary, AB T2E 7M9Dwayne Dale
Calgary Project Office | Morgan Construction and Environmental Ltd.

Innovative Well Abandonment
Address
11630 Kingsway NW,Edmonton, AB T5G 0X5